We are able to offer complete solution for tank welding with various design approach, each base-to-top and top-to-base tank building, hydraulic lifting program are particularly created for leading-to-base tank erection.

The pursuing brief description offers the working procedure in outline. It can in certain information be modified when needed.
 
Action 1.  The tank bottom – plates are placed on the ready basis and welded jointly.
Stage 2.  The beams or lattice work of the roof are assembled and lastly joined to the higher rim of the shell ring.
Step 3.  The jacking tools is set up in the tank. The plates of the next shell ring (next to the prime ring) are positioned outdoors the very first one.
Step4.   The finished portion of the tank (roof and prime shell ring) is lifted hydraulically to a top at which the plates of the 2nd ring can be moved into place and the roof sheeting can be finished.
Step5.   The plates of the 2nd shell ring are located precisely and welded with each other to the lower edge of the very first ring.
Step6.   The plates of the 3rd shell ring are placed outdoors the next shell ring.
Step7.   The concluded component of the tank (roof the two uppermost shell rings) is lifted.
Step8.   The earlier mentioned cycle of operations is repeated until finally the very last (base) shell ring is completed.
Step9.    The complete tank is reduced down to the bottom plate and welded to this.
Step10.  The lifting gear is dismantled.